| Task Name | Duration |
| Prescaffold Errection | 20 days |
| Execution | 40 days |
| Run Up Commissioning | 10 days |
23 days - Boiler Mechanical 18/05/26 to 17/06/26
(White Collar, Fitter, Boilermaker, Tubewelder, TA/Hole Watcher)
34 days - Turbine 6/05/26 to 22/06/26
(White Collar, Fitter, TA, Crane Driver)
69 days - Scaffold 7/04/26 to 11/07/26
(Scaffolders)
40 days - Insulation 5/05/26 to 29/06/26
(Lagger/SMW)
26 days - NDT Tech 18/05/26 to 20/06/26
(NDT Tech)
40 days - NRG STEs 5/05/26 to 29/06/26
(Casuals: Electrician, E&I. Boilermaker, Fitter, TA, Rigger)
Dign Unit #2 - 2d Tue 3/3/26 - Thu 3/5/26
Fitters - 120
Riggers - 40
TA - 20
10 Mill 6 Month Outage - 1d Sun 4/19/26 - Mon 4/20/26
QAL Internal Resource - 12
Dign Unit #3 - 2d Tue 6/2/26 - Thu 6/4/26
Fitters - 120
Riggers - 40
TA - 20
Dign Unit #1 - 2d Tue 8/25/26 - Thu 8/27/26
Fitters - 12
Riggers - 40
TA - 20
10 Mill 12 Month Outage - 2d Fri 10/16/26 - Sun 10/18/26
QAL Internal Resource - 12
GSC #2 Minor, FSC Coils & Gas - 42d - Sun 5/31/26 - Sun 7/12/26
Fitters - 30
Refractory - 10
Scaffolders - 10
Lurgi Gas- 14d - Sun 10/18/26 - Sun 11/1/26
Refractory - 50
Fitters - 50
Scaffolders 50
Fitters - 12
Siemens - 65
Scaffolders - 25
Insulation - 15
Refractory - 8
Electrical - 10
NDT - 6
Welders - 18
Riggers 6
GSC #2 Minor & Gas - 14d - Sun 3/7/27 - Sun 3/21/27
Fitters - 30
Refractory - 10
Scaffolders - 10
GSC #1 Minor, FSC Coils & Gas - 14d - Sun 5/2/27 - Sun 5/16/27
Fitters - 30
Refractory - 10
Scaffolders - 10
Lurgi Gas- 42d - Sun 6/13/27 - Sun 7/25/27
Refractory - 50
Fitters - 50
Scaffolders 50
314 workforce required
Dign Unit #2 - 2d - Wed 3/3/27 to Fri 3/5/27
Fitters - 120
Riggers - 40
TA - 20
Dign Unit #3 - 2d - Wed 6/2/27 to Fri 6/4/27
Fitters - 120
Riggers - 40
TA - 20
Dign Unit #1 - 2d - Wed 8/25/27 to Fri 8/27/27
Fitters - 12
Riggers - 40
TA - 20
633 workforce required
314 workforce required
633 workforce required